We appreciate your visit to i If 12 men can complete a piece of work in 72 days in how many days will 24 men do the same work ii. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

i) If 12 men can complete a piece of work in 72 days, in how many days will 24 men do the same work?

ii) Find the final amount to be paid to the bank if Rs. 7000 is borrowed for 4 years at a rate of 6% per annum.

Answer :

Answer:

1. 36 days, 2. $8,680

Step-by-step explanation:

1. We know that 12 men can do the work in 72 days, so if you add double the men, it will take half the time. Half of 72 is 36, so our answer is 36 days.

2. If $7,000 is borrowed, that person owes $7,000 so far, but they keep it for 4 years with an annual interest rate of 6%. To solve this, we need to find 6% of 7,000. To do this, we multiply 7,000 by .06. That gets us 420. Now, we multiply 420 by 4. That gets us 1,680. Now, we add 1,680 and 7,000. That gets us 8,680. That means the final amount owed is $8,680.

Thanks for taking the time to read i If 12 men can complete a piece of work in 72 days in how many days will 24 men do the same work ii. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!

Rewritten by : Barada

Answer:

Question 1 answer is 144

Step-by-step explanation:

just multiply