We appreciate your visit to A small metal shop operates 10 hours each day producing 100 parts per hour If productivity were increased by 20 a What is the new. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Step-by-step explanation:
a. To find the new productivity, first calculate the increase in productivity:
Increase in productivity = 20% of 100 parts/hour
= 0.2 x 100
= 20 parts/hour
New productivity = Old productivity + Increase in productivity
= 100 + 20
= 120 parts/hour
Now the new productivity is 120 parts/hour.
b. To find the number of hours required to produce 1000 parts, we can use:
Number of hours = Number of parts ÷ Productivity
Substituting the given values, we get:
Number of hours = 1000 ÷ 120
= 8.33 hours
So the plant would have to work for 8.33 hours to produce 1000 parts at the new productivity level.
if this was helpful, kindly give me a brainliest rating.
Thanks for taking the time to read A small metal shop operates 10 hours each day producing 100 parts per hour If productivity were increased by 20 a What is the new. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada