We appreciate your visit to If the static budget variance for materials is 250 F and the budgeted cost for materials is 52 000 then the actual cost of materials. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

If the static budget variance for materials is $250 F and the budgeted cost for materials is $52,000, then the actual cost of materials is:

A. $51,750
B. $51,950
C. $51,150
D. $52,150

Answer :

Answer:

Option A is correct: $51750

Explanation:

Since static budget variance for materials is favourable;hence actual cost is less than the budgeted cost.


hence actual cost=(52000-250)

=$51750.

Thanks for taking the time to read If the static budget variance for materials is 250 F and the budgeted cost for materials is 52 000 then the actual cost of materials. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!

Rewritten by : Barada

Answer:

a. $51,750

Explanation:

Given:

Budget = $52,000

Variance = 250 F

Actual cost of materials = budget - variance

$52,000 - 250

= $51,750