We appreciate your visit to If the static budget variance for materials is 250 F and the budgeted cost for materials is 52 000 then the actual cost of materials. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Answer:
Option A is correct: $51750
Explanation:
Since static budget variance for materials is favourable;hence actual cost is less than the budgeted cost.
hence actual cost=(52000-250)
=$51750.
Thanks for taking the time to read If the static budget variance for materials is 250 F and the budgeted cost for materials is 52 000 then the actual cost of materials. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada
Answer:
a. $51,750
Explanation:
Given:
Budget = $52,000
Variance = 250 F
Actual cost of materials = budget - variance
$52,000 - 250
= $51,750