College

We appreciate your visit to Webster Corporation is preparing a master budget for the first quarter of the year The company budgets production of 2 940 units in January 2. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

Webster Corporation is preparing a master budget for the first quarter of the year. The company budgets production of 2,940 units in January, 2,730 units in February, and 3,390 units in March. Each unit requires 0.6 hours of direct labor. The direct labor rate is $12 per hour.

Compute the budgeted direct labor cost for the first quarter.

Answer :

Answer:

65,232

Explanation:

Webster Corporation

Budgeted direct labor cost for quarter

= Total production * hours required * rate

= (2940+2730+3390)*0.6*12

=$9,060*7.2

= 65,232

Thanks for taking the time to read Webster Corporation is preparing a master budget for the first quarter of the year The company budgets production of 2 940 units in January 2. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!

Rewritten by : Barada

Answer:

Budgeted labour cost for the quarter = $60,480

Explanation:

The labour budget shoes the estomated cost of labour hours required to achieve the production budget.

Direct labour budget:

Total production for the first quarter = 2,940 + 2,730 + 3,390 =8400 units

The labour budget in hours = Total production unit × standard hour

= 8400 × 0.6 hours

= 5040 hours

Total labour budget i ($) = Total labour hours × rate per hour

= 5040 × $12