We appreciate your visit to You are managing a design project The initial estimate of work hours required was 3 860 You have 4 engineers assigned to the project full. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
The duration of a design project can be calculated based on the original estimate of work hours and the progress made so far.
How can the duration of the project be calculated based on the given information?
Based on the given information, 65% of the design work has been completed at a cost of $62,000. This means that the actual cost of the work completed is 65% of the total estimated cost, or 0.65 * 3860 * 30 = $75,270.
To calculate the remaining cost of the project, we subtract the cost of the work completed from the estimated cost: 3860 * 30 - 75,270 = $34,530.
To estimate the remaining duration of the project, we can divide the remaining work (in hours) by the amount of work that can be completed in a week by the team. The team consists of 4 engineers working full-time (8 hours per day, 5 days per week) and one engineer working half-time (4 hours per day, 5 days per week), for a total of 4 * 8 + 0.5 * 4 * 8 = 36 hours per day or 180 hours per week.
The remaining work is 34,530 / 30 = 1,151 hours. Dividing this by 180 hours per week gives us approximately 6.4 weeks, or 7 weeks rounded up.
Therefore, based on the original estimate of 3,860 work hours and the progress made so far, the duration of the project is estimated to be 13 + 7 = 20 weeks.
Learn more about project management and cost estimation.
brainly.com/question/31435686
#SPJ11
Thanks for taking the time to read You are managing a design project The initial estimate of work hours required was 3 860 You have 4 engineers assigned to the project full. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada