We appreciate your visit to The single milling machine at Stout Manufacturing was severely overloaded last year The plant operates eight hours per day five days per week and 50. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Final answer:
Stout Manufacturing will need at least 3 new milling machines to meet the demand for products A and B, considering production and setup time as well as the desired capacity cushion.
Explanation:
To calculate the number of new milling machines required at Stout Manufacturing, we must first determine the total annual hours needed for both products and then compare this to the available machine hours per year, taking into account the desired capacity cushion.
First, let's calculate the total hours needed for production and setup for each product independently:
Annual hours for product A (production + setup) = (Annual demand / Batch size) * (Standard processing time * Batch size + Standard setup time) = (3000 / 20) * (0.5 * 20 + 2) = 150 * 12 = 1800 hours
Annual hours for product B (production + setup) = (2000 / 40) * (0.8 * 40 + 8) = 50 * 40 = 2000 hours
Combined annual hours for A and B = 1800 + 2000 = 3800 hours
The total available hours per year for one machine is calculated as follows:
Available hours per machine per year (with cushion) = Operating hours per day * Days per week * Weeks per year * (1 - capacity cushion) = 8 * 5 * 50 * (1 - 0.15) = 1700 hours
Now, we divide the combined annual hours by the available hours per machine to find the number of machines required:
Number of machines required = Total annual hours / Available hours per machine per year = 3800 / 1700 ≈ 2.24
Since you cannot have a fraction of a machine, Stout Manufacturing will need to round up, meaning they require at least 3 new milling machines to meet the demand without resorting to short-term capacity options.
Thanks for taking the time to read The single milling machine at Stout Manufacturing was severely overloaded last year The plant operates eight hours per day five days per week and 50. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada
Answer:
If we assumes we setup machine for product A x times, and B y times, the total hours required is 0.5*3000 + 0.8*2000+ 2*x + 8 *y = 3100+2x+8y. Notice that due to the capacity restriction x has to be no smaller than 150 hours (3000/20) and y has to be no smaller than 50 hours (2000/40). so total required hours must exceed 3100+2*150+8*50=3800. The management prefer a 15% capacity cushion, which means the total duration prepared for the processing should be at least 3800*(1+15%)=4370 hours.
If one machine operates eight hours per day, five days per week and 50 weeks a year, it operates 5*8*50 = 2000 hours in total.