We appreciate your visit to A project has the following risks 20 probability of a 14 day delay in the receipt of customer requirements 10 probability of a 21 day. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Final answer:
The expected value of the project delays is 4.9 days, calculated by multiplying each delay duration by its probability and summing the results.
Explanation:
The question provided asks for the expected value of project delays given certain probabilities and durations of those delays. To calculate the expected value of these risks, we multiply each delay by its corresponding probability, and then sum the results.
The first risk is a 20 percent probability (0.20) of a 14-day delay, and the second risk is a 10 percent probability (0.10) of a 21-day delay. Following the formula for expected value, we would calculate:
- (0.20 * 14 days) + (0.10 * 21 days)
- (2.8 days) + (2.1 days)
- 4.9 days
Hence, the expected value of the delays is 4.9 days. This means that on average, the project can be expected to be delayed by about 4.9 days due to these risks. This is a project management calculation widely used in risk analysis and planning.
Thanks for taking the time to read A project has the following risks 20 probability of a 14 day delay in the receipt of customer requirements 10 probability of a 21 day. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada