We appreciate your visit to Jay and Morgan work in the summer for a landscaper It takes Jay 3 hours to complete the company s largest yard alone If Morgan. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

Jay and Morgan work in the summer for a landscaper. It takes Jay 3 hours to complete the company's largest yard alone. If Morgan helps him, it takes only 1 hour. How much time would it take Morgan alone to complete the yard?

Answer :

it would take Morgan 3/2 hours (or 1 hour and 30 minutes) to complete the yard alone.

Let's assume that Morgan's time to complete the yard alone is represented by "M" hours. We know that when Jay and Morgan work together, they finish the yard in 1 hour. In one hour, Jay completes 1/3 of the yard (since it takes him 3 hours alone), and Morgan completes 1/M of the yard.

When they work together, their combined efficiency adds up, so we can set up the equation:

1/3 + 1/M = 1.

To find M, we can solve this equation for M. Multiplying through by 3M gives:

M + 3 = 3M,

2M = 3,

M = 3/2.

Learn more about equation here:

https://brainly.com/question/29657983

#SPJ11

Thanks for taking the time to read Jay and Morgan work in the summer for a landscaper It takes Jay 3 hours to complete the company s largest yard alone If Morgan. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!