We appreciate your visit to In a truck loading operation the arrival rate for loading trucks is 13 trucks per hour and the average service time is 3 7 minutes. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
The mean time between arrivals, or interarrival time in a truck-loading operation, given an arrival rate of 13 trucks per hour, is roughly 4.615 minutes.
The primary concept of this question lies in the field of operations management, particularly in queuing theory, an area of mathematics. The arrival rate, denoted usually by λ (lambda), represents the number of clients that arrive at the system per unit of time.
Given that the arrival rate here is 13 trucks per hour, the mean time between arrivals, also known as interarrival time or waiting time, can be found by the inverse of the arrival rate.
To convert the arrival rate from trucks per hour to trucks per minute, because there are 60 minutes in an hour, divide 13 trucks per hour by 60 to get an arrival rate of approximately 0.2167 trucks per minute.
Therefore, the mean time between arrivals is the reciprocal of this value, which is approximately 4.615 minutes. This means, on average, a new truck arrives every 4.615 minutes.
Learn more about the topic of Queuing Theory here:
https://brainly.com/question/33964562
#SPJ11
Thanks for taking the time to read In a truck loading operation the arrival rate for loading trucks is 13 trucks per hour and the average service time is 3 7 minutes. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada