We appreciate your visit to A contractor has a crew of two individuals a backhoe operator and a helper working in the Lost Woods They are building a small lake. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

A contractor has a crew of two individuals (a backhoe operator and a helper) working in the Lost Woods. They are building a small lake for an international house cat dock jumping event. The anticipated lake size is 1 acre in area and averages 5 feet deep.

a. Assuming a flat area, calculate the amount of material to be excavated (assume no soil expansion). [5%]

b. Assuming, based on the equipment being used, that 150 cubic yards (CY) can be removed per 8-hour shift (and assume 1 shift per day); how many days will it take to complete the project (round to the whole number)? [5%]

c. If on Mondays and Fridays, production is only 100 CY per day and no work happens on Saturday/Sunday, how many weeks will it take to complete the work? [5%]

d. If the operator and helper (including equipment usage, material, and overhead) is $200 per hour (hourly rate is for a full 8-hour shift, even if a partial day), using the production rates in part c, how much will labor and material cost? [5%]

e. If a 30% markup is required to maintain profitability, how much should your rate be per cubic yard of material removed? [5%]

Answer :

a)Total material to be excavated: 1,613 cubic yards

b) Number of days to complete the work: 11 days

c) Number of weeks to complete the work: 2 weeks

d) Labor and material cost: $17,600

e) Rate per cubic yard of material removed: $260

a) The volume of the lake:

Area of the lake = 1 acre

Average depth of the lake = 5 feet

Convert the area to square feet: 1 acre = 43,560 square feet

Volume of the lake = Area × Depth = 43,560 cubic feet

Convert the volume to cubic yards: 43,560 / 27 = 1,613 cubic yards

b) The number of days to complete the work:

The contractor can remove 150 cubic yards of material in 1 shift.

Divide the total volume of the lake by the amount removed in a shift: 1,613 / 150 = 10.75 ≈ 11 days

c) The number of weeks to complete the work:

The contractor removes 100 cubic yards of material per day for 2 days of the week.

The contractor removes 150 cubic yards of material per day for the remaining 5 days of the week.

Calculate the total amount of material removed in a week:

(100 × 2) + (150 × 5) = 950 cubic yards

Divide the total volume of the lake by the amount removed in a week:

1,613 / 950 = 1.7 ≈ 2 weeks (rounded to whole number)

d) The labor and material cost:

The cost of the operator and helper per hour is $200.

Calculate the total production:

Amount produced on Mondays and Fridays

=100 cubic yards per day × 2 days = 200 cubic yards

Amount produced on the remaining 5 days

= 150 cubic yards per day × 5 days = 750 cubic yards

Total production in the first week

= 200 + 750 = 950 cubic yards

The total hours worked in the first week:

Hours worked on Mondays and Fridays

= 2 days × 8 hours/day = 16 hours

Hours worked on the remaining 5 days

= 5 days × 8 hours/day = 40 hours

Total hours worked in the first week

= 16 + 40 = 56 hours

The labor and material cost in the first week:

Labor and material cost per hour = $200

Total labor and material cost in the first week

= 56 hours × $200/hour = $11,200

The amount produced in the second week and total hours worked:

Amount produced in the second week = Total volume - Amount produced in the first week

= 1,613 - 950 = 663 cubic yards

Total hours worked in the second week

= 3 days × 8 hours/day + 2 days × 8 hours/day = 32 hours

The labor and material cost in the second week:

Labor and material cost in the second week = Total hours worked in the second week × $200/hour

= 32 hours × $200/hour = $6,400

Total labor and material cost = Labor and material cost in the first week + Labor and material cost in the second week = $11,200 + $6,400 = $17,600

e) The rate per cubic yard of material removed:

A 30% markup is required.

Calculate the markup amount: 30% × $200 = $60

Calculate the rate per cubic yard: $200 + $60 = $260 per cubic yard

To know more about Volume visit:

https://brainly.com/question/29255732

#SPJ11

Thanks for taking the time to read A contractor has a crew of two individuals a backhoe operator and a helper working in the Lost Woods They are building a small lake. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!