We appreciate your visit to A master budget calls for 3 000 units of production and budgeted fixed overhead of 6 000 Actual production was 3 500 units and total. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

A master budget calls for 3,000 units of production and budgeted fixed overhead of $6,000. Actual production was 3,500 units and total fixed overhead was $6,150. The spending variance is ______.

A. $150 U
B. $850 U
C. $150 F
D. $850 F

Answer :

Spending variance, also known as expenditure variance or cost variance, is a measure used in budgeting and variance analysis to assess the difference between the budgeted or expected amount of spending and the actual amount of spending incurred. The correct answer is $150 f.

Actual fixed overhead: $6,150
Budgeted fixed overhead: $6,000

Spending Variance = Actual Fixed Overhead - Budgeted Fixed Overhead

Spending Variance = $6,150 - $6,000 = $150 F (favorable)

The spending variance is $150 F, which means that the actual fixed overhead was $150 less than the budgeted fixed overhead.

In this case, the company spent $150 less than expected on fixed overhead. This could be due to cost-saving measures or efficiencies in the production process. It is a favourable variance because it indicates that the company has saved money on fixed overhead expenses compared to the budgeted amount.

Therefore, the correct answer is $150 F.

To know more about Spending variance visit:

https://brainly.com/question/32106354

#SPJ11

Thanks for taking the time to read A master budget calls for 3 000 units of production and budgeted fixed overhead of 6 000 Actual production was 3 500 units and total. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!