We appreciate your visit to Daniel the production manager was pleased with the company s income statement results The actual direct labor DL cost was 56 400 compared to the. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Final answer:
The company's DL price variance is -$7,300 and DL efficiency variance is $3,675.
Explanation:
To calculate the DL price variance, we need to find the difference between the actual DL cost and the budgeted DL cost. The actual DL cost is given as $56,400, and the budgeted DL cost is $63,700. Therefore, the DL price variance can be calculated as:
DL Price Variance = Actual DL Cost - Budgeted DL Cost
DL Price Variance = $56,400 - $63,700
DL Price Variance = -$7,300
The negative value indicates that the actual DL cost is lower than the budgeted DL cost, resulting in a favorable variance.
To calculate the DL efficiency variance, we need to find the difference between the actual DL hours and the budgeted DL hours, multiplied by the budgeted DL rate. The actual DL hours are given as 2,350, and the budgeted DL hours can be calculated by multiplying the number of units produced and sold (1,100) by the budgeted DL hours per unit (2 hours).
Budgeted DL Hours = Number of Units * Budgeted DL Hours per Unit
Budgeted DL Hours = 1,100 * 2
Budgeted DL Hours = 2,200
DL Efficiency Variance = (Actual DL Hours - Budgeted DL Hours) * Budgeted DL Rate
DL Efficiency Variance = (2,350 - 2,200) * $24.50
DL Efficiency Variance = 150 * $24.50
DL Efficiency Variance = $3,675
The positive value indicates that the actual DL hours used were higher than the budgeted DL hours, resulting in an unfavorable variance.
Learn more about calculating dl price and dl efficiency variances here:
https://brainly.com/question/34575230
#SPJ11
Thanks for taking the time to read Daniel the production manager was pleased with the company s income statement results The actual direct labor DL cost was 56 400 compared to the. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada