We appreciate your visit to 19 Shirkashi Construction Company Limited commenced construction for a building on 01 01 2023 for a contract price of Rs 600000 The following is the. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
To address the question, let's start by preparing the Contract Account for Shirkashi Construction Company Limited.
1. Contract Account for the year ending 31/12/2023:
[tex]\begin{align*}
\text{Particulars} & \text{Rs} & \ \ \ \text{Particulars} & \text{Rs} \\
\hline
\text{To Materials} & 60,000 & \ \ \ \text{By Materials at Site} & 11,000 \\
\text{To Wages} & 75,000 & \ \ \ \text{To Closing Stock (Certified)} & 240,000 \\
\text{To Other Expenses} & 25,000 & \ \ \ \text{By Material Returned} & 5,000 \\
\text{To Supervisor's Salary} & 60,000 & \ \ \ \text{By Plant Destroyed} & 5,000 \\
\text{To Plant} & 35,000 & \ \ \ \text{By Plant Depreciation (20\% of 40,000)} & 8,000 \\
\text{To Cost of Work Done but Not Certified} & 19,000 & \ \ \ \text{To Contractee's A/C} & 192,000 \\
\hline
\text{Total} & 274,000 & \ \ \ \text{Total} & 269,000 \\
\end{align*}[/tex]
Notes for Contract Account:
- Depreciation on Plant is calculated at 20% of Rs 40,000, which is Rs 8,000.
- Only 80% of the certified work's value is paid by the contractee. Therefore, certified work is [tex]\frac{240,000}{0.8} = 300,000[/tex].
2. Balance Sheet as of 31/12/2023:
Assets:
- Current Assets:
- Cash at Bank: Rs 60,000
- Materials at Site: Rs 11,000
- Non-Current Assets:
- Plant: Rs 27,000 (after depreciation of Rs 8,000 and reduction for returned/damaged)
Liabilities:
- Share Capital: Rs 80,000
- Contractee's A/C: Rs 240,000 (from the work paid)
- Outstanding Wages: Not specified but usually part of the liabilities if any exist
Equity and Liabilities:
The remaining balances would normally be adjusted for profits and outstanding expenses.
In conclusion, the contract account shows the expenses incurred and the revenue recognized, while the balance sheet reflects the company's financial position.
Thanks for taking the time to read 19 Shirkashi Construction Company Limited commenced construction for a building on 01 01 2023 for a contract price of Rs 600000 The following is the. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada