We appreciate your visit to involves formal acceptance of the completed project scope by the stakeholders A Scope validation B Scope baseline C Scope control D Scope planning. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

_____ involves formal acceptance of the completed project scope by the stakeholders.

A. Scope validation
B. Scope baseline
C. Scope control
D. Scope planning

Answer :

Final answer:

The formal acceptance of the completed project scope by the stakeholders refers to Scope Validation. It involves confirming the completion of work and deliverables outlined in the project scope, and fixing any discrepancies discovered. It differs from scope baseline, scope planning, and scope control.

Explanation:

In the context of project management, when you are talking about the formal acceptance of the completed project scope by the stakeholders, you are referring to Scope Validation.

Scope validation is a critical step in which the stakeholders confirm that all the work and deliverables outlined in the project scope have been successfully completed. If any discrepancies are discovered during this process, rectification occurs immediately. For example, if a software development project has the deliverable of designing a user-friendly interface with specified functionalities, during scope validation, stakeholders will check these functionalities. If anything is lacking or incorrectly implemented, this process ensures those issues are fixed before declaring project completion.

In contrast, the scope baseline constitutes the original project plan plus approved changes. Scope planning refers to the process of creating a project scope management plan, and scope control is about controlling changes to the project scope.

Learn more about Scope Validation here:

https://brainly.com/question/32383205

#SPJ11

Thanks for taking the time to read involves formal acceptance of the completed project scope by the stakeholders A Scope validation B Scope baseline C Scope control D Scope planning. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!