We appreciate your visit to An agile project has a release duration of 3 months This release is executed through 3 sprints each lasting 4 weeks How many minimum planning. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

An agile project has a release duration of 3 months. This release is executed through 3 sprints, each lasting 4 weeks. How many minimum planning meetings are required for this overall release?

a) 6 planning meetings: 3 release planning and 3 sprint planning meetings
b) 5 planning meetings: 2 release planning (one at the start and one in the middle) and 3 sprint planning meetings
c) 4 planning meetings: 1 release planning and 3 sprint planning meetings
d) 3 sprint planning meetings only

Answer :

Final answer:

The correct option of the given statement "A release cycle for an agile project lasts three months. This release is carried out over the course of 3 sprints, with each sprint lasting 4 weeks. How many planning sessions are necessary for this release overall??" is c) 4 planning meeting i.e., 1 release planning and 3 sprint planning meetings.

Explanation:

In Agile Project Management, both release planning and sprint planning meetings are important. Release planning sets the high-level scope and agenda for the entire project, while sprint planning organizes work on a smaller scale for each sprint. In the case presented, the release duration is executed over three sprints.

This would mean one release planning meeting at the start of the project, and then a sprint planning meeting at the start of each sprint. Therefore, a minimum of four planning meetings are required for this release: one release planning and three sprint planning meetings.

With that considered, the correct answer is (c) 4 planning meetings i.e., 1 release planning and 3 sprint planning meetings.

Learn more about the topic of Agile Project here: brainly.com/question/30916733

#SPJ11




Thanks for taking the time to read An agile project has a release duration of 3 months This release is executed through 3 sprints each lasting 4 weeks How many minimum planning. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!