We appreciate your visit to A project is budgeted for 2400 hours and will last 3 weeks Technicians will cover 25 of the project in the first week and 60. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Final answer:
The project requires 15 technicians for the first week and 18 technicians for the final two weeks to be completed as per the given schedule.
Explanation:
The project has a total project timeline of 2400 hours spread over 3 weeks. In the first week, technicians cover 25% of this work, which amounts to 600 hours (2400 * 0.25). In the final two weeks, they cover 60% of the work, which equals 1440 hours (2400 * 0.6).
If each technician normally works for 40 hours in a week, then the total number of technician hours for the first week is 600 / 40 = 15 technicians. For the final two weeks, where each week has 40 hours, we have a total of 80 hours available per technician. The 1440 hours would then require 1440 / 80 = 18 technicians.
So, the project requires 15 technicians for the first week and 18 technicians for the final two weeks to be completed on the planned schedule.
Learn more about Work and Time here:
https://brainly.com/question/3854047
#SPJ1
Thanks for taking the time to read A project is budgeted for 2400 hours and will last 3 weeks Technicians will cover 25 of the project in the first week and 60. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada