We appreciate your visit to Sigma Ltd manufactures a single product the standard mix of which is Material A 60 at Rs 20 per kg Material B 40 at Rs. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

Sigma Ltd. manufactures a single product, the standard mix of which is:

Material A 60% at Rs. 20 per kg.
Material B 40% at Rs. 10 per kg.

Normal loss in production is 20% of input. Due to shortage of Material A, the standard mix was changed. Actual results for March, 1999 were:

Material A 105 kg. at Rs. 20 per kg.
Material B 95 kg. at Rs. 9 per kg.
Input 200 kg.
Loss 35 kg.
Output 165 kg.

Calculate all material variances.

Answer :

To calculate material variances, we need to consider several components: Material Cost Variance (MCV), Material Price Variance (MPV), Material Usage Variance (MUV), and Material Mix and Yield Variances. Here's a step-by-step approach to find these variances.

Standard Mix Proportions:

  • Material A: 60%
  • Material B: 40%

Standard Prices:

  • Material A: Rs. 20 per kg
  • Material B: Rs. 10 per kg

Actual Input and Prices:

  • Material A: 105 kg at Rs. 20 per kg
  • Material B: 95 kg at Rs. 9 per kg

Actual Output:

  • Loss: 35 kg
  • Output: 165 kg

Total Input: 200 kg

Normal Loss: 20% of 200 = 40 kg

Therefore, standard output should be 200 - 40 = 160 kg

Material Cost Variance (MCV):

[tex]MCV = (Standard Cost of Actual Output) - (Actual Cost)[/tex]

1. Calculate Standard Cost of Actual Output:

For 165 kg output, considering 80% of input (normal yield is 160 kg for 200 kg input),

  • Standard Input = [tex]\frac{165}{160} \times 200 = 206.25 \text{ kg of input}[/tex]

  • Material A = 60% of 206.25 = 123.75 kg

  • Material B = 40% of 206.25 = 82.5 kg

Standard cost of Material A = 123.75 \times 20 = Rs. 2,475

Standard cost of Material B = 82.5 \times 10 = Rs. 825

Total Standard Cost = Rs. 2,475 + Rs. 825 = Rs. 3,300

2. Actual Cost:

  • Actual Cost of Material A = 105 \times 20 = Rs. 2,100
  • Actual Cost of Material B = 95 \times 9 = Rs. 855

Actual Total Cost = Rs. 2,100 + Rs. 855 = Rs. 2,955

[tex]MCV = 3,300 - 2,955 = Rs. 345 \text{ (Favorable)}[/tex]

Material Price Variance (MPV):

[tex]MPV = \sum \left( (Standard Price - Actual Price) \times Actual Quantity \right)[/tex]

  • MPV for Material A = (20 - 20) \times 105 = Rs. 0

  • MPV for Material B = (10 - 9) \times 95 = Rs. 95

Total MPV = Rs. 95 (Favorable)

Material Usage Variance (MUV):

[tex]MUV = \sum \left( (Standard Quantity for Actual Output - Actual Quantity) \times Standard Price \right)[/tex]

  • MUV for Material A = (123.75 - 105) \times 20 = Rs. 375

  • MUV for Material B = (82.5 - 95) \times 10 = -Rs. 125

Total MUV = Rs. 375 - Rs. 125 = Rs. 250 (Favorable)

These calculated variances provide insights into the efficiency and cost control of materials in the production process for Sigma Ltd.

Thanks for taking the time to read Sigma Ltd manufactures a single product the standard mix of which is Material A 60 at Rs 20 per kg Material B 40 at Rs. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!