We appreciate your visit to Additional Sample Problems on Capacity Planning XYZ company is producing a solar panel for street lighting which is composed of 80 solar cells The company. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

**Additional Sample Problems on Capacity Planning**

XYZ company is producing a solar panel for street lighting, which is composed of 80 solar cells. The company has 10 solar tabber and stringer machines at any given time. These machines allow soldering and assembling the cells together to compose the photovoltaic cell at the rate of 50 pieces per hour. The man-machine ratio is 1:1.

Currently, the company has 6 technicians per shift, and they are working 3 shifts in a day with a 75-minute break. They have 5 working days per week and 4 weeks in a month.

How many panels can they produce in one month?

Answer :

The number of panels they can produce in one month is 2843.

To calculate the panels produced in one month:

We need to calculate the total available working hours in one month

First, we will calculate the total working hours per day

Total working hours per day = (Number of shifts per day x Working hours per shift) - Total break time per shift

Total working hours per day = (3 x 8) - (1.25 x 60)

Total working hours per day = 24 - 75

Total working hours per day = 22.75

Now, we will calculate the total available working hours in one month.

Total working hours in a month = Total working hours per day x Number of working days in a month

Total working hours in a month = 22.75 x 5 x 4

Total working hours in a month = 455

We have a man-machine ratio of 1:1. It means that we need one technician for every solar tabber and stinger machine.

So, Total number of technicians required = Number of solar tabber and stinger machines available

Total number of technicians required = 10

Now, the productivity of the technician can be calculated as, Productivity of a technician = Productivity of one solar tabber and stinger machine

Productivity of a technician = 50 pcs/hour

So, The total productivity in a month = Productivity of one technician x Number of technicians x Total working hours in a month.

The total productivity in a month = 50 x 10 x 455

The total productivity in a month = 227500

Hence, the company can produce 227500/80 = 2843 panels in one month.

Learn more about productivity here: https://brainly.com/question/21044460

#SPJ11

Thanks for taking the time to read Additional Sample Problems on Capacity Planning XYZ company is producing a solar panel for street lighting which is composed of 80 solar cells The company. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!