We appreciate your visit to Rob is responsible for estimating a work package with significant uncertainty regarding time and cost He will make low average and high estimates Rob is. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

Rob is responsible for estimating a work package with significant uncertainty regarding time and cost. He will make low, average, and high estimates. Rob is using which estimating approach?

Answer :

Answer:

Range estimating.

Explanation:

Range estimation is an estimation approach that allows an interested person to have much relevant information about the nature of a task being set. Through this estimate it is possible to have more confidence or more uncertainty in a project that is being stipulated and that may result in a large profit or a great loss.

Thanks for taking the time to read Rob is responsible for estimating a work package with significant uncertainty regarding time and cost He will make low average and high estimates Rob is. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!

Rewritten by : Barada