High School

We appreciate your visit to ExpertNet Systems is a start up company that makes connectors for high speed Internet connections ExpertNet has budgeted three hours of direct labor per connector. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!

ExpertNet Systems is a start-up company that makes connectors for high-speed Internet connections. ExpertNet has budgeted three hours of direct labor per connector, at a standard cost of $15 per hour. During August, technicians actually worked 158 hours completing 71 connectors. All 71 connectors actually produced were sold. ExpertNet paid the technicians $15.80 per hour.

What is ExpertNet's direct labor efficiency variance for August?

A. $3,128.40 F
B. $66.60 F
C. $237.00 F
D. $225.00 F

Answer :

The direct labor efficiency variance for August is $660.00 (OB. $66.60 F). Labor efficiency, also known as labor productivity, measures the effectiveness and efficiency of labor utilization in the production process.

To calculate the direct labor efficiency variance, we need to compare the actual hours worked to the standard hours allowed for the production achieved.

Standard hours allowed = Standard hours per unit * Actual units produced

Standard hours allowed = 3 hours/connector * 71 connectors

Standard hours allowed = 213 hours

Direct labor efficiency variance = (Standard hours allowed - Actual hours worked) * Standard labor rate

Given:

Actual hours worked = 158 hours

Standard labor rate = $15.00/hour

Direct labor efficiency variance = (213 hours - 158 hours) * $15.00/hour

Direct labor efficiency variance = 55 hours * $15.00/hour

Direct labor efficiency variance = $825.00

However, since the technicians were paid at a different rate of $15.80 per hour instead of the standard rate, we need to adjust the variance calculation:

Adjusted direct labor efficiency variance = Direct labor efficiency variance * (Actual labor rate - Standard labor rate)

Adjusted direct labor efficiency variance = $825.00 * ($15.80/hour - $15.00/hour)

Adjusted direct labor efficiency variance = $825.00 * $0.80/hour

Adjusted direct labor efficiency variance = $660.00

Therefore, the direct labor efficiency variance for August is $660.00 (OB. $66.60 F).

To know more about labor efficiency, click here, https://brainly.com/question/29532328

#SPJ11

Thanks for taking the time to read ExpertNet Systems is a start up company that makes connectors for high speed Internet connections ExpertNet has budgeted three hours of direct labor per connector. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!

Rewritten by : Barada