We appreciate your visit to Heavey Compressors uses a lean production assembly line to make its compressors In one assembly area the demand is 100 parts per eight hour day. This page offers clear insights and highlights the essential aspects of the topic. Our goal is to provide a helpful and engaging learning experience. Explore the content and find the answers you need!
Answer :
Heavey Compressors should be using 13 containers for the assembly area. The maximum system inventory for this part is 104 parts. If the safety stock percentage is reduced to zero, the number of containers required would remain the same.
a. To determine the number of containers needed, we first need to calculate the production time required for the demand. In an eight-hour day, with a demand of 100 parts, each container holding eight parts, the total number of containers needed can be calculated as follows:
Number of containers = (Demand / Parts per container) + Safety stock
= (100 / 8) + (0.15 * 100 / 8)
= 12.5 + 1.875
≈ 13
Therefore, Heavey Compressors should be using 13 containers in the assembly area.
b. The maximum system inventory can be calculated by multiplying the number of containers by the parts per container:
Maximum system inventory = Number of containers * Parts per container
= 13 * 8
= 104 parts
Hence, the maximum system inventory for this part is 104 parts.
c. If the safety stock percentage is reduced to zero, the number of containers required would remain the same. The safety stock percentage affects the additional inventory needed to account for uncertainty in demand or supply. However, in this case, the number of containers is determined solely based on the demand and production time. Since the safety stock percentage does not impact the production time or the container capacity, reducing it to zero would not change the number of containers required.
In conclusion, Heavey Compressors should use 13 containers in the assembly area to meet the demand of 100 parts per eight-hour day. The maximum system inventory for this part is 104 parts. If the safety stock percentage is reduced to zero, the number of containers required would remain the same.
Learn more about percentage here:
https://brainly.com/question/32397578
#SPJ11
Thanks for taking the time to read Heavey Compressors uses a lean production assembly line to make its compressors In one assembly area the demand is 100 parts per eight hour day. We hope the insights shared have been valuable and enhanced your understanding of the topic. Don�t hesitate to browse our website for more informative and engaging content!
- Why do Businesses Exist Why does Starbucks Exist What Service does Starbucks Provide Really what is their product.
- The pattern of numbers below is an arithmetic sequence tex 14 24 34 44 54 ldots tex Which statement describes the recursive function used to..
- Morgan felt the need to streamline Edison Electric What changes did Morgan make.
Rewritten by : Barada